Somer Valley Links – Update Nov 2026
Phase 1 of the Somer Valley Links project is underway across the area aiming to improve travel between Midsomer Norton, Radstock and Bath via the A367, Bristol via the A37, and the A362 link road.
Published: 20 November 2026
The works will take place between October 2026 and February 2027, with a pause during Christmas:
- A raised continuous crossing at the Ham Lane/A37 Bristol Road junction, level with the pavement. This is to slow approaching vehicles and prioritise pedestrians.
- An upgraded crossing at the Pitway Lane and Church Lane junctions with the A37 Bristol Road. It will include resurfacing and tactile paving. (Tactile paving is for blind and partially sighted people to navigate crossings)
- The entrance to both Ham Lane and Church Lane will be raised to slow traffic approaching the junction.
- Resurfacing the pedestrian area at the Main Street/A37 Bristol Road junction. It will also add new cycle parking and a bike repair station at the Main Street bus stop.
- Wider footways on both sides of the A37 Bristol Road between the upgraded Ham Lane bus shelter and the bus stop opposite Pitway Lane.
- A new signal-controlled crossing on the A37 Bristol Road between the Church Lane and Pitway Lane junctions. This will replace the existing central refuge island.
- An upgraded northbound bus shelter at Ham Lane on the A37 Bristol Road. It will have new seating, a green roof and real-time bus information.
- Real-time bus information at the Main Street bus stop.
To confirm, there will be no speed bumps on the A37 within Farrington Gurney.